NRC OPERATIONS CENTER PLANT STATUS REPORT FOR 05/16/94 UNEVALUATED INFORMATION PROVIDED BY THE FACILITY ------------------------------------------------ REG PLANT NAME PHONE %PWR DOWN RESTART REASON OR COMMENT * # --- --------------------- ----- ---- ----- ------- ------------------------ - - 1 BEAVER VALLEY 1 2201 000 05/07 UNK MODE 5 - COLD SHUTDOWN MAKING REPAIR TO REACTOR PLANT RIVER WATER HEADER. SEE EVENT 27218 -------------------------------------------------------------------------------- 1 BEAVER VALLEY 2 2201 100 -------------------------------------------------------------------------------- 1 CALVERT CLIFFS 1 2202 002 MODE 2 - STARTUP HOLDING TO RESOLVE PROBLEM WITH SGFP CONTROL -------------------------------------------------------------------------------- 1 CALVERT CLIFFS 2 2202 000 05/15 05/29 MODE 3 - HOT STANDBY * MAINTENANCE OUTAGE - VOLTAGE REGULATOR TESTING AND SERVICE WATER WORK -------------------------------------------------------------------------------- 1 FITZPATRICK 1 2203 100 -------------------------------------------------------------------------------- 1 GINNA 1 2204 097 -------------------------------------------------------------------------------- 1 HADDAM NECK 1 2205 100 -------------------------------------------------------------------------------- 1 HOPE CREEK 1 2206 000 05/15 UNK COND 4 - COLD SHUTDOWN * # RX SCRAM DUE TO LOW REACTOR VESSEL WATER LEVEL - SEE EVENT #27254 - CURRENT ESTIMATE IS 5- 6 DAY OUTAGE TO REPLACE "B" RX RECIRC PUMP SEAL PACKAGE -------------------------------------------------------------------------------- 1 INDIAN POINT 2 2207 090 SG TUBE LEAKAGE-LEAK RATE <0.01 GPM. -------------------------------------------------------------------------------- 1 INDIAN POINT 3 2208 000 02/93 10/01 MODE 5 - COLD SHUTDOWN MAINTENANCE OUTAGE -------------------------------------------------------------------------------- 1 LIMERICK 1 2209 100 -------------------------------------------------------------------------------- 1 LIMERICK 2 2209 100 -------------------------------------------------------------------------------- 1 MAINE YANKEE 1 2210 100 -------------------------------------------------------------------------------- 1 MILLSTONE 1 2211 000 01/15 05/18 COND 4 - COLD SHUTDOWN REFUELING OUTAGE -------------------------------------------------------------------------------- 1 MILLSTONE 2 2211 000 04/23 05/20 MODE 5 - COLD SHUTDOWN * MAINTENANCE OUTAGE - VENTING RX COOLANT PUMPS -------------------------------------------------------------------------------- 1 MILLSTONE 3 2212 100 -------------------------------------------------------------------------------- 1 NINE MILE POINT 1 2213 100 -------------------------------------------------------------------------------- 1 NINE MILE POINT 2 2213 100 -------------------------------------------------------------------------------- 1 OYSTER CREEK 1 2215 100 -------------------------------------------------------------------------------- 1 PEACH BOTTOM 2 2216 000 05/15 05/22 COND 3 - HOT SHUTDOWN * # RX SCRAM DUE TO APRM HI FLUX - SEE EVENT #27256 - 7 DAY OUTAGE TO BALANCE "B" RFP TURBINE AND REPLACE "A" RX RECIRC PUMP SEAL PACKAGE -------------------------------------------------------------------------------- 1 PEACH BOTTOM 3 2216 100 -------------------------------------------------------------------------------- 1 PILGRIM 1 2217 100 -------------------------------------------------------------------------------- 1 SALEM 1 2218 000 04/07 05/18 MODE 4 - HOT SHUTDOWN * MAINTENANCE OUTAGE - CURRENTLY HEATING UP -------------------------------------------------------------------------------- 1 SALEM 2 2218 100 -------------------------------------------------------------------------------- 1 SEABROOK 1 2219 000 04/08 06/06 MODE 6 - REFUELING DEFUELED -------------------------------------------------------------------------------- 1 SUSQUEHANNA 1 2221 100 -------------------------------------------------------------------------------- 1 SUSQUEHANNA 2 2221 000 03/14 06/02 COND 5 - REFUELING * CORE RELOAD IN PROGRESS - SHOULD COMPLETE TODAY -------------------------------------------------------------------------------- 1 THREE MILE ISLAND 1 2222 100 -------------------------------------------------------------------------------- 1 VERMONT YANKEE 1 2224 100 -------------------------------------------------------------------------------- NRC OPERATIONS CENTER PLANT STATUS REPORT FOR 05/16/94 UNEVALUATED INFORMATION PROVIDED BY THE FACILITY ------------------------------------------------ REG PLANT NAME PHONE %PWR DOWN RESTART REASON OR COMMENT * # --- --------------------- ----- ---- ----- ------- ------------------------ - - 2 BROWNS FERRY 1 2229 000 03/85 UNK COND 5 - REFUELING DEFUELED -------------------------------------------------------------------------------- 2 BROWNS FERRY 2 2229 100 -------------------------------------------------------------------------------- 2 BROWNS FERRY 3 2229 000 03/85 UNK COND 5 - REFUELING DEFUELED -------------------------------------------------------------------------------- 2 BRUNSWICK 1 2230 100 -------------------------------------------------------------------------------- 2 BRUNSWICK 2 2230 000 03/26 06/28 COND 5 - REFUELING DEFUELED -------------------------------------------------------------------------------- 2 CATAWBA 1 2231 100 -------------------------------------------------------------------------------- 2 CATAWBA 2 2231 000 04/29 06/15 MODE 6 - REFUELING DEFUELED -------------------------------------------------------------------------------- 2 CRYSTAL RIVER 3 2233 000 04/06 06/07 MODE 6 - REFUELING * CORE RELOADED - PLAN TO INSTALL PLENUM TODAY -------------------------------------------------------------------------------- 2 FARLEY 1 2234 100 -------------------------------------------------------------------------------- 2 FARLEY 2 2234 099 -------------------------------------------------------------------------------- 2 GRAND GULF 1 2235 100 -------------------------------------------------------------------------------- 2 HARRIS 1 2236 073 HOLDING FOR FLUX MAP * THEN INCREASING POWER IN 10% INCREMENTS FOR POWER ASCENSION TESTING -------------------------------------------------------------------------------- 2 HATCH 1 2237 100 -------------------------------------------------------------------------------- 2 HATCH 2 2237 100 -------------------------------------------------------------------------------- 2 MCGUIRE 1 2239 100 -------------------------------------------------------------------------------- 2 MCGUIRE 2 2239 100 -------------------------------------------------------------------------------- 2 NORTH ANNA 1 2240 100 -------------------------------------------------------------------------------- 2 NORTH ANNA 2 2240 100 -------------------------------------------------------------------------------- 2 OCONEE 1 2241 000 04/28 06/16 MODE 6 - REFUELING REFUELING OUTAGE - DEFUELED -------------------------------------------------------------------------------- 2 OCONEE 2 2241 100 -------------------------------------------------------------------------------- 2 OCONEE 3 2241 100 -------------------------------------------------------------------------------- 2 ROBINSON 2 2242 100 -------------------------------------------------------------------------------- 2 SEQUOYAH 1 2243 100 -------------------------------------------------------------------------------- 2 SEQUOYAH 2 2243 100 -------------------------------------------------------------------------------- 2 ST LUCIE 1 2244 100 -------------------------------------------------------------------------------- 2 ST LUCIE 2 2244 100 -------------------------------------------------------------------------------- 2 SUMMER 1 2245 100 -------------------------------------------------------------------------------- 2 SURRY 1 2246 100 -------------------------------------------------------------------------------- 2 SURRY 2 2246 089 REDUCED POWER DUE TO LEVEL SWINGS IN SG "C". -------------------------------------------------------------------------------- 2 TURKEY POINT 3 2247 000 04/03 05/19 MODE 3 - HOT STANDBY * WILL PERFORM LOW POWER PHYSICS TESTING TODAY -------------------------------------------------------------------------------- 2 TURKEY POINT 4 2247 100 -------------------------------------------------------------------------------- 2 VOGTLE 1 2248 100 -------------------------------------------------------------------------------- 2 VOGTLE 2 2248 100 -------------------------------------------------------------------------------- NRC OPERATIONS CENTER PLANT STATUS REPORT FOR 05/16/94 UNEVALUATED INFORMATION PROVIDED BY THE FACILITY ------------------------------------------------ REG PLANT NAME PHONE %PWR DOWN RESTART REASON OR COMMENT * # --- --------------------- ----- ---- ----- ------- ------------------------ - - 3 BIG ROCK POINT 1 2250 096 -------------------------------------------------------------------------------- 3 BRAIDWOOD 1 2251 028 HOLDING FOR CHEMISTRY * AND FLUX MAP - ENFORCEMENT DISCRETION GRANTED FOR TRAIN "A" EDG INOPERABLE AND UNIT 2 TRAIN "A" EDG OOS FOR PLANNED MAINT -------------------------------------------------------------------------------- 3 BRAIDWOOD 2 2251 000 04/05 06/01 MODE 5 - COLD SHUTDOWN * REFUELING OUTAGE -------------------------------------------------------------------------------- 3 BYRON 1 2252 099 -------------------------------------------------------------------------------- 3 BYRON 2 2252 099 -------------------------------------------------------------------------------- 3 CALLAWAY 1 2253 100 -------------------------------------------------------------------------------- 3 CLINTON 1 2270 100 -------------------------------------------------------------------------------- 3 COOK 1 2254 000 02/12 05/21 MODE 5 - COLD SHUTDOWN * MAINTENANCE OUTAGE - LEAK REPAIR ON THE #4 CORE EXIT T/C -------------------------------------------------------------------------------- 3 COOK 2 2254 063 FUEL CONSERVATION -------------------------------------------------------------------------------- 3 DAVIS BESSE 1 2255 100 -------------------------------------------------------------------------------- 3 DRESDEN 2 2256 100 * -------------------------------------------------------------------------------- 3 DRESDEN 3 2256 000 03/10 05/30 COND 5 - REFUELING DEFUELED -------------------------------------------------------------------------------- 3 DUANE ARNOLD 1 2257 100 -------------------------------------------------------------------------------- 3 FERMI 2 2258 000 12/93 10/01 COND 5 - REFUELING DEFUELED -------------------------------------------------------------------------------- 3 KEWAUNEE 1 2259 074 HOLDING <75% FOR NI * VERIFICATION -------------------------------------------------------------------------------- 3 LASALLE 1 2261 000 02/18 06/01 COND 5 - REFUELING CORE RELOADED -------------------------------------------------------------------------------- 3 LASALLE 2 2261 100 * -------------------------------------------------------------------------------- 3 MONTICELLO 1 2263 100 -------------------------------------------------------------------------------- 3 PALISADES 1 2264 000 02/17 UNK MODE 5 - COLD SHUTDOWN MAINTENANCE OUTAGE - FILL AND VENT SCHEDULED FOR 6/4 -------------------------------------------------------------------------------- 3 PERRY 1 2265 000 02/06 06/22 COND 5 - REFUELING DEFUELED -------------------------------------------------------------------------------- 3 POINT BEACH 1 2266 100 * -------------------------------------------------------------------------------- 3 POINT BEACH 2 2266 099 -------------------------------------------------------------------------------- 3 PRAIRIE ISLAND 1 2267 000 05/07 06/25 MODE 6 - REFUELING * REFUELING OUTAGE - RV HEAD WILL BE REMOVED FOR CORE OFFLOAD TODAY -------------------------------------------------------------------------------- 3 PRAIRIE ISLAND 2 2267 100 -------------------------------------------------------------------------------- 3 QUAD CITIES 1 2268 000 03/13 07/03 COND 5 - REFUELING DEFUELED -------------------------------------------------------------------------------- 3 QUAD CITIES 2 2268 097 ADMINISTRATIVE LIMIT DUE TO FLOW UNCERTAINTY -------------------------------------------------------------------------------- 3 ZION 1 2269 000 04/03 06/11 MODE 5 - COLD SHUTDOWN REPLACING MAIN TRANSFORMER -------------------------------------------------------------------------------- 3 ZION 2 2269 100 -------------------------------------------------------------------------------- NRC OPERATIONS CENTER PLANT STATUS REPORT FOR 05/16/94 UNEVALUATED INFORMATION PROVIDED BY THE FACILITY ------------------------------------------------ REG PLANT NAME PHONE %PWR DOWN RESTART REASON OR COMMENT * # --- --------------------- ----- ---- ----- ------- ------------------------ - - 4 ARKANSAS NUCLEAR 1 2271 100 -------------------------------------------------------------------------------- 4 ARKANSAS NUCLEAR 2 2271 100 -------------------------------------------------------------------------------- 4 COMANCHE PEAK 1 2272 058 HOLDING FOR REPAIR OF FEED PUMP OIL LEAK -------------------------------------------------------------------------------- 4 COMANCHE PEAK 2 2272 000 04/22 05/22 MODE 5 - COLD SHUTDOWN MAINTENANCE OUTAGE -------------------------------------------------------------------------------- 4 COOPER 1 2273 098 INCREASING POWER TO 100% * -------------------------------------------------------------------------------- 4 DIABLO CANYON 1 2281 000 05/10 05/22 MODE 5 - COLD SHUTDOWN * REPAIRING FAULT ON THE "C" PHASE OF THEIR MAIN BANK TRANSFORMER -------------------------------------------------------------------------------- 4 DIABLO CANYON 2 2281 100 -------------------------------------------------------------------------------- 4 FT CALHOUN 1 2274 100 -------------------------------------------------------------------------------- 4 PALO VERDE 1 2282 086 ADMIN LIMIT OF 86% POWER DUE TO STRESS CORROSION IN THE STEAM GENERATORS -------------------------------------------------------------------------------- 4 PALO VERDE 2 2283 042 ADMIN LIMIT OF 86% POWER * DUE TO STRESS CORROSION IN THE STEAM GENERATORS - INCREASING POWER TO 86% -------------------------------------------------------------------------------- 4 PALO VERDE 3 2284 000 03/18 06/04 MODE 5 - COLD SHUTDOWN * REFUELING OUTAGE -------------------------------------------------------------------------------- 4 RIVER BEND 1 2276 000 04/16 06/08 COND 5 - REFUELING * RECOUPLING CONTROL BLADES -------------------------------------------------------------------------------- 4 SAN ONOFRE 2 2287 098 -------------------------------------------------------------------------------- 4 SAN ONOFRE 3 2287 097 SG HEAT XFER PROBLEMS -------------------------------------------------------------------------------- 4 SOUTH TEXAS 1 2277 100 -------------------------------------------------------------------------------- 4 SOUTH TEXAS 2 2277 000 02/93 05/17 MODE 3 - HOT STANDBY * -------------------------------------------------------------------------------- 4 WASHINGTON NUCLEAR 2 2289 000 04/26 06/30 COND 5 - REFUELING * REFUELING OUTAGE - CORE RELOAD IN PROGRESS -------------------------------------------------------------------------------- 4 WATERFORD 3 2278 100 -------------------------------------------------------------------------------- 4 WOLF CREEK 1 2279 100 -------------------------------------------------------------------------------- * - REASON OR COMMENT HAS BEEN CHANGED IN PAST 24 HOURS # - NUMBER OF REACTOR SCRAMS WITHIN PAST 24 HOURS NOTE - REACTOR STATUS DATA COLLECTED BETWEEN 4 A.M. AND 8 A.M. EACH DAY. ALL TIMES ARE BASED ON EASTERN TIMES (ET).