Headquarters Daily report FEBRUARY 06, 1995 *************************************************************************** REPORT NEGATIVE NO INPUT ATTACHED INPUT RECEIVED RECEIVED HEADQUARTERS X REGION I X REGION II X REGION III X REGION IV X *************************************************************************** PRIORITY ATTENTION REQUIRED MORNING REPORT - HEADQUARTERS FEB. 06, 1995 Licensee/Facility: Notification: Part 21 Database MR Number: H-95-0048 Cooper Energy Services Date: 02/06/95 Subject: Reportable Event Number: N/A Discussion: VENDOR: COOPER ENERGY SERVICES PT21 FILE NO: 95039 (COOPER-BESSEMER) DATE OF DOCUMENT: 02/01/95 ACCESSION NUMBER: SOURCE DOCUMENT: MR REVIEWER: OECB: E. GOODWIN NIAGARA MOHAWK POWER/NINE MILE POINT 2 REPORTS INSTABILITY OF EDG PERFORMANCE DUE TO OVERHEATING OF MECHANICAL GOVERNOR. GOV COOLER MAY BE RECEIVING INADEQUATE COOLING FLOW. GOV REPLACED. INVEST UNDERWAY. PRIORITY ATTENTION REQUIRED MORNING REPORT - HEADQUARTERS FEB. 06, 1995 Licensee/Facility: Notification: Part 21 Database MR Number: H-95-0049 Colt Industries Date: 02/06/95 Subject: Reportable Event Number: N/A Discussion: VENDOR: COLT INDUSTRIES PT21 FILE NO: 95040 DATE OF DOCUMENT: 04/20/94 ACCESSION NUMBER: 9501270231 SOURCE DOCUMENT: Part 21 REVIEWER: OECB: R.DENNIG COLTEC INDUSTRIES/FMED REPORTS LACK OF SEISMIC ANALYSIS FOR TRANSFER PUMP CONTROL SWITCH & FOOT VALVE FOR DAY TANK FOR EDG DOES NOT CONSTITUTE A SSH. PROVIDES RESULTS OF EVALUATION. SEE LOG# 94070/94302. PRIORITY ATTENTION REQUIRED MORNING REPORT - HEADQUARTERS FEB. 06, 1995 Licensee/Facility: Notification: Part 21 Database MR Number: H-95-0050 Auma Date: 02/06/95 Subject: Reportable Event Number: N/A Discussion: VENDOR: AUMA PT21 FILE NO: 95041 DATE OF DOCUMENT: 02/03/95 ACCESSION NUMBER: SOURCE DOCUMENT: 50.72 REVIEWER: OECB: E. GOODWIN CONNECTICUT YANKEE APC/HADDAM NECK REPORTS FAILURE OF TWO MO SERVICE WATER BYPASS VALVES TO FULLY OPEN DUE TO TRIPPING OF TORQUE SWITCH. TS SETTING FOUND TO BE OK PER MNFCTR. RESET TO HIGHER SETTING & VALVE OPER PROPERLY. INVEST CAUSE OF PROB. PRIORITY ATTENTION REQUIRED MORNING REPORT - HEADQUARTERS FEB. 06, 1995 Licensee/Facility: Notification: Part 21 Database MR Number: H-95-0051 Westinghouse Date: 02/06/95 Subject: Reportable Event Number: N/A Discussion: VENDOR: WESTINGHOUSE PT21 FILE NO: 95042 DATE OF DOCUMENT: 02/03/95 ACCESSION NUMBER: SOURCE DOCUMENT: 50.72 REVIEWER: OECB: R. DENNIG VIRGINIA ELECTRIC POWER/NORTH ANNA 1/2 REPORTS SSPS DECLARED INOP DUE TO POTENTIAL OF SHORTING OF TURBINE TRIP PROTECTION CIRCUITS IN EVENT OF STEAMLINE BREAK. SIMILAR TO DIABLO CANYON & SALEM PROB. PLANTS UNDERGOING SHUTDOWN. PRIORITY ATTENTION REQUIRED MORNING REPORT - HEADQUARTERS FEB. 06, 1995 MR Number: H-95-0052 NRR DAILY REPORT ITEM GENERIC COMMUNICATIONS BRANCH/EVENTS ASSESSMENT BRANCH DIVISION OF OPERATING REACTOR SUPPORT OFFICE OF NUCLEAR REACTOR REGULATION Subject: N/A NRC Administrative Letter 95-01, Supplement 1, "Change in Commercial Telephone and Facsimile Numbers at Nuclear Regulatory Commission Headquarters," was issued February 2, 1995. The NRC issued this administrative letter supplement to inform addressees that the NRC Operations Center commercial telephone and facsimile 24-hour numbers have not been changed even though most telephone numbers at the NRC have been changed, as announced in the original administrative letter. Contacts: Henry A. Bailey, AEOD (301) 415-7483 C. Vernon Hodge, NRR (301) 415-1861 NRC Information Notice 95-10, "Potential for Loss of Automatic Engineered Safety Features Actuation," was issued February 3, 1995. The NRC issued this information notice to alert addressees to the potential for loss of the automatic actuation function of engineered safety features (ESF) as a result of electrical faults in some non-class 1E input signals. Technical contacts: E. Nick Fields, NRR (301) 415-1173 Cliff Doutt, NRR (301) 415-2847 PRIORITY ATTENTION REQUIRED MORNING REPORT - REGION III FEBRUARY 6, 1995 Licensee/Facility: Notification: Northern States Power Co. MR Number: 3-95-0009 Prairie Island 1 2 Date: 02/06/95 Welch,Minnesota VIA LICENSEE Dockets: 50-282,50-306 PWR/W-2-LP,PWR/W-2-LP Subject: DEMONSTRATION Reportable Event Number: N/A Discussion: On February 4, 1995, a planned demonstration was held at the Prairie Island Nuclear Power Station to protest dry cask storage. Approximately 100 people participated in the demonstration, which took place at the entrance to the owner controlled area approximately a quarter mile from the facility. There were no arrests, no damage to property and no injuries reported. Officials from the State and local police monitored the event. Regional Action: Information Only. Contact: J. R. CREED (708)829-9857