Headquarters Daily report MAY 16, 1994 *************************************************************************** REPORT NEGATIVE NO INPUT ATTACHED INPUT RECEIVED RECEIVED HEADQUARTERS X REGION I X REGION II X REGION III X REGION IV X *************************************************************************** PRIORITY ATTENTION REQUIRED MORNING REPORT - REGION III MAY 16, 1994 Licensee/Facility: Notification: Commonwealth Edison Co. MR Number: 3-94-0095 Braidwood 1 Date: 05/13/94 Braceville,Illinois SRI VIA PC Dockets: 50-456 PWR/W-4-LP Subject: UNIT 1 STARTUP FOLLOWING A PLANNED REFUELING OUTAGE Reportable Event Number: N/A Discussion: On May 13, 1994, Unit 1 was synchronized to the grid, ending a 71-day refueling outage. Major activities accomplished during the outage included a full core offload and refueling, extensive high pressure turbine and low pressure "A" turbine work, 125V ESF train A and B battery replacements, and 100 percent steam generator eddy current inspection. During the steam generator inspections, a significant number of tubes (