Subject: Williston Basin Interstate Pipeline Company; Amended
[Federal Register: October 15, 2002 (Volume 67, Number 199)]
[Notices]
[Page 63643-63645]
>From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr15oc02-69]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP02-37-000]
Williston Basin Interstate Pipeline Company; Amended Notice of
Intent To Prepare an Environmental Impact Statement for the Proposed
Grasslands Project and Request for Comments on Environmental Issues
October 8, 2002.
As previously noticed on February 5, 2002, and amended herein, the
staff of the Federal Energy Regulatory Commission (FERC or Commission)
will prepare an environmental impact statement (EIS) that will discuss
the environmental impacts of the Grasslands Project, as amended,
involving construction, operation, and abandonment of facilities by
Williston Basin Interstate Pipeline Company (WBI).\1\ WBI proposes to
construct new pipeline and appurtenant facilities in Wyoming, Montana,
and North Dakota to transport 80,000 (rather than the originally
proposed 120,000) thousand cubic feet per day (Mcf/d) of natural gas
from the Powder River Basin to its storage facilities in Montana and to
the Northern Border Pipeline Company's system in North Dakota. This EIS
will be used by the Commission in its decision-making process to
determine whether the project is in the public convenience and
necessity.
---------------------------------------------------------------------------
\1\ WBI's application was filed with the Commission under
sections 7(b) and (c) of the Natural Gas Act on November 30, 2001,
and amended on September 27, 2002.
---------------------------------------------------------------------------
The FERC will be the lead Federal agency for the preparation of the
EIS. The Miles City Field Office of the U.S. Department of the
Interior's Bureau of Land Management (BLM), the Medora Ranger District
of the U.S. Department of Agriculture's Forest Service (FS), and the
Montana Department of Environmental Quality (MTDEQ) will be cooperating
with us in the preparation of the EIS. Meetings with the MTDEQ, BLM,
and FS were held January 14, 15, and 16, 2002, respectively, to discuss
procedural and potential environmental issues for this project.\2\
Other Federal, state, and tribal agencies with jurisdiction and/or
special expertise with respect to environmental issues may also request
cooperating agency status.
---------------------------------------------------------------------------
\2\ Summaries of these meetings have been placed in the public
file in this docket.
---------------------------------------------------------------------------
If you are a landowner receiving this notice, you may be contacted
by a pipeline company representative about the acquisition of an
easement to construct, operate, and maintain the proposed facilities.
The pipeline company would seek to negotiate a mutually acceptable
agreement. However, if the project is approved by the Commission, that
approval conveys with it the right of eminent domain. Therefore, if
easement negotiations fail to produce an agreement, the pipeline
company could initiate condemnation proceedings in accordance with
state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' was attached to the
project notice WBI provided to landowners. This fact sheet addresses a
number of typically asked questions, including the use of eminent
domain and how to participate in the Commission's proceedings. It is
available for viewing on the FERC Internet Web site (www.ferc.gov).
This notice is being sent to landowners of property crossed by and
adjacent to both WBI's originally proposed route and their currently
proposed route, as filed in WBI's September 27, 2002 Amendment filing
(the EIS will evaluate both routes); tenants and lessees on affected
public land; Federal, state, and local agencies; elected officials;
Indian tribes that might attach religious and cultural significance to
historic properties in the
[[Page 63644]]
area of potential effects; environmental and public interest groups;
and local libraries and newspapers. State and local government
representatives are encouraged to notify their constituents of this
proposed action and encourage them to comment on their areas of
concern.
Summary of the Proposed Project (as Amended on September 27, 2002)
The proposed facilities consist of about 248 miles of pipeline and
5,329 (rather than the originally proposed 12,540) horsepower (hp) of
compression. Additionally, WBI is seeking to abandon certain other
pipeline facilities in Wyoming and Montana. WBI also has revised its
construction schedule, proposing to construct the Grasslands Project in
three phases. Specifically, WBI seeks authority to:
• Construct approximately 219 miles of new 16-inch-diameter
pipeline from near Belle Creek, Montana, to the proposed Manning
Compressor Station in Dunn County, North Dakota (no change, except for
approximately 69.5 miles of proposed route realignments);
• Construct approximately 28 miles of 16-inch-diameter
pipeline loop \3\ adjacent to its existing Bitter Creek supply lateral
pipeline in Wyoming (no change, except for approximately 2.6 miles of
proposed route realignments);
---------------------------------------------------------------------------
\3\ A loop is a segment of pipeline that is usually installed
adjacent to an existing pipeline and connected to it at both ends.
The loop allows more gas to be moved through the system.
---------------------------------------------------------------------------
• Increase the maximum allowable operating pressure (MAOP) on
approximately 28 miles of its existing 8-inch-diameter Bitter Creek
supply lateral pipeline in Wyoming from 1,203 pounds per square inch
gauge (psig) to 1,440 psig, and abandon in place segments of existing
pipe at three road crossings and replace them with heavier walled pipe
(new, per amended filing);
• Increase the MAOP on approximately 40 miles of its existing
8-inch-diameter Recluse-Belle Creek supply lateral pipeline in Wyoming
and Montana from 1,203 pounds per square inch gauge (psig) to 1,440
psig, and abandon in place segments of existing pipe at eight road
crossings and replace them with heavier walled pipe (no change);
• Construct 4,180 hp of gas fired compression (comprised of
two 2,090 hp compressors) at one new compressor station located in Dunn
County, North Dakota (Manning Compressor Station), and install electric
coolers rather than running the coolers off the horsepower produced at
the station (previously, WBI was proposing two more additional
compressor stations, each with 4,180 hp);
• Install an additional transmission compressor unit (1,200
hp) at the existing Cabin Creek Compressor Station in Fallon County,
Montana (new, per amended filing);
• Construct 0.9 mile of 12-inch-diameter pipeline from the
proposed mainline to the existing Cabin Creek Compressor Station in
Fallon County, Montana (no change, except that this line would have
connected the previously proposed Cabin Creek South Compressor Station
to the existing Cabin Creek Compressor Station);
• Construct 1.0 mile of 16-inch-diameter pipeline from the
proposed Manning Compressor Station to interconnect with Northern
Border Pipeline Company's Compressor Station 5 in Dunn County, North
Dakota (no change); and
• Construct various additional facilities, including 14
mainline valves, 4 cathodic protection units, 8 pig launchers/receivers
(2 fewer than previously proposed), 5 metering stations (2 fewer than
previously proposed), and 2 regulators (3 fewer than previously
proposed).
WBI indicates in its September 27, 2002 Amended filing that it will
no longer be necessary to build an amine treatment facility as part of
its proposal.
The general location of the project facilities is shown in appendix
1.\4\
---------------------------------------------------------------------------
\4\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies are available on the
Commission's Web site at the ``FERRIS'' link or from the
Commission's Public Reference and Files Maintenance Branch, 888
First Street, NE., Washington, DC 20426, or call 1-866-208-3676. For
instructions on connecting to FERRIS refer to the last page of this
notice. Copies of the appendices were sent to all those receiving
this notice in the mail.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of WBI's proposed pipeline facilities would require
about 3,124.8 acres of land including the construction right-of-way,
extra workspaces, and contractor/pipe yards, and access roads. WBI
proposes to use a 100-foot-wide construction right-of-way. Following
construction and restoration of the right-of-way and temporary work
spaces, WBI would retain a 50-foot-wide permanent pipeline right-of-
way. Total land requirements for the permanent right-of-way would be
about 1,526.1 acres, some of which would overlap existing rights-of-
way.
WBI proposes to acquire 10 acres for the proposed Manning
Compressor Station. The entire 10 acre parcel could be disturbed during
construction and would be fenced following construction. WBI also will
require 0.33 acre of land for the Cabin Creek tie-in in Fallon County,
Montana.
The EIS Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\5\ to discover and address concerns the public may have about
proposals. We call this ``scoping''. The main goal of the scoping
process is to focus the analysis in the EIS on the important
environmental issues. By this Notice of Intent, the Commission requests
public comments on the scope of the issues it will address in the EIS.
All comments received are considered during the preparation of the EIS.
State and local government representatives are encouraged to notify
their constituents of this proposed action and encourage them to
comment on their areas of concern.
---------------------------------------------------------------------------
\5\ ''We'', ``us'', and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
Our independent analysis of the impacts that could occur as a
result of the construction and operation of the proposed project will
be in the Draft EIS. The Draft EIS will be mailed to Federal, state,
and local agencies, public interest groups, affected landowners and
other interested individuals, Indian tribes, newspapers, libraries, and
the Commission's official service list for this proceeding. A 45-day
comment period will be allotted for review of the Draft EIS. We will
consider all comments on the Draft EIS and revise the document, as
necessary, before issuing a Final EIS. The Final EIS will include our
response to each comment received on the Draft EIS and will be used by
the Commission in its decision-making process to determine whether to
approve the project.
To ensure your comments are considered, please carefully follow the
instructions in the public participation section beginning on page 6.
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the environmental
information provided by WBI and discussions with the cooperating
agencies. This preliminary list of issues may be changed based on your
comments and our analysis.
[[Page 63645]]
• Geology
--Impact on mineral resources
--Paleontological concerns
• Cultural Resources
--Impact on the proposed Custer-Sully Historic Corridor
• Soils and Vegetation
• Construction on steep slopes
--Noxious weeds
--Seed mixes for restoration
--Loss of riparian vegetation
• Water Resources and Wetlands
--Use of directional drilling
--Ensuring pipe is placed below scour depth
• Wildlife and Fisheries
--Impact on bighorn sheep habitat
--Impact on raptor nesting and roosting areas
--Impact on sage grouse habitat
• Endangered and Threatened Species
--Impact on Federally-listed species
--Impact on FS, BLM, and state sensitive species
• Socioeconomic Impacts
• Public Safety
• Cumulative Impacts
--Discussion of regional coal bed methane development
• Air Quality and Noise
--Visibility degradation
--Compressor station emissions
--Noise from compressor stations
• Alternative Routes and Site Locations
--Co-location with other pipelines may not be feasible in certain areas
across Little Missouri National Grasslands
--Abandonment method for road crossings (in-place vs. removal)
• Land Use
--Use of access roads on public land
--Impact on planned residential or commercial development
--Ensuring access across the right-of-way for cattle during
construction
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. By becoming a commentor, your
concerns will be addressed in the EIS and considered by the Commission.
You should focus on the potential environmental effects of the
proposal, alternatives to the proposal (including alternative
locations/routes), and measures to avoid or lessen environmental
impact. The more specific your comments, the more useful they will be.
Please carefully follow these instructions to ensure that your comments
are received in time and properly recorded:
• Send an original and two copies of your letter to: Magalie
R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First
St., NE., Room 1A, Washington, DC 20426.
• Label one copy of the comments for the attention of OEP--
Gas 1, PJ-11.1.
• Reference Docket No. CP02-37-000.
• Mail your comments so that they will be received in
Washington, DC on or before November 8, 2002.
Please note that we are continuing to experience delays in mail
deliveries from the U.S. Postal Service. As a result, we will include
all comments that we receive within a reasonable time frame in our
environmental analysis of this project. However, the Commission
strongly encourages electronic filing of any comments or interventions
or protests to this proceeding. See 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission's Web site at http://www.ferc.gov under
the ``e-Filing'' link and the link to the User's Guide. Before you can
file comments you will need to create an account which can be created
by clicking on ``Login to File'' and then ``New User Account.''
All commentors will be retained on our mailing list. If you do not
want to send comments at this time but still want to stay informed and
receive copies of the Draft and Final EISs, you must return the
attached Information Request (appendix 3). Note: If you have already
sent comments in response to the February 5, 2002 Notice, you do not
need to send them again to be retained on the mailing list. If you do
not send, or have not sent, comments or return the Information Request,
you will be taken off the mailing list.
Becoming an Intervenor
In addition to involvement in the EIS scoping process, you may want
to become an official party to the proceeding known as an
``intervenor''. Intervenors play a more formal role in the process.
Among other things, intervenors have the right to receive copies of
case-related Commission documents and filings by other intervenors.
Likewise, each intervenor must provide 14 copies of its filings to the
Secretary of the Commission and must send a copy of its filings to all
other parties on the Commission's service list for this proceeding. If
you want to become an intervenor you must file a motion to intervene
according to rule 214 of the Commission's rules of practice and
procedure (18 CFR 385.214) (see appendix 2).\6\ Only intervenors have
the right to seek rehearing of the Commission's decision.
---------------------------------------------------------------------------
\6\ Interventions may also be filed electronically via the
Internet in lieu of paper. See the previous discussion on filing
comments electronically.
---------------------------------------------------------------------------
Affected landowners and parties with environmental concerns may be
granted intervenor status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which would not be
adequately represented by any other parties. You do not need intervenor
status to have your environmental comments considered.
Environmental Mailing List
This notice is being sent to individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project. It is also being sent to all identified potential
right-of-way grantors. By this notice we are also asking governmental
agencies to express their interest in becoming cooperating agencies for
the preparation of the EIS.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (www.ferc.gov) using the FERRIS link. Click on
the FERRIS link, enter the docket number excluding the last three
digits in the Docket Number field. Be sure you have selected an
appropriate date range. For assistance with FERRIS, the FERRIS helpline
can be reached at 1-866-208-3676, TTY (202) 502-8659, or at
ferconlinesupport@ferc.gov. The FERRIS link on the FERC Internet Web
site also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rulemakings.
Linwood A. Watson, Jr.,
Deputy Secretary.
[FR Doc. 02-26076 Filed 10-11-02; 8:45 am]
BILLING CODE 6717-01-P