Subject: Plymouth Generating Facility
[Federal Register: January 22, 2002 (Volume 67, Number 14)]
[Notices]
[Page 2868-2869]
>From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr22ja02-56]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Bonneville Power Administration
Plymouth Generating Facility
AGENCY: Bonneville Power Administration (BPA), Department of Energy
(DOE).
ACTION: Notice of intent to prepare an Environmental Impact Statement
(EIS).
-----------------------------------------------------------------------
SUMMARY: This notice announces BPA's intention to prepare a joint
National Environmental Policy Act (NEPA)/State Environmental Policy Act
(SEPA) EIS in cooperation with Benton County, State of Washington, for
an electrical interconnection including a new one-mile transmission
line and other facilities associated with a proposed powerplant. BPA is
the lead Federal agency under NEPA and Benton County is the lead
Washington State agency under SEPA. The Plymouth Generating Facility is
a 306-megawatt (MW) generating station proposed by Plymouth Energy,
L.L.C. (PE) that would be located near the town of Plymouth in Benton
County, Washington. PE has requested an interconnection to BPA's
transmission system that would allow firm power delivery to the
wholesale power market. BPA proposes to execute an agreement with PE to
provide the interconnection and firm power transmission.
ADDRESSES: To be placed on the project mailing list, including
notification of proposed meetings, call toll-free 1-800-622-4520, name
this project, and leave your complete name and address. To comment,
call toll-free 1-800-622-4519; send an e-mail to the BPA Internet
address comment@bpa.gov; or send a letter to Communications, Bonneville
Power Administration--KC-7, PO Box 12999, Portland, Oregon, 97212.
FOR FURTHER INFORMATION, CONTACT: Philip W. Smith, Bonneville Power
Administration--KEC-4, PO Box 3621, Portland, Oregon, 97208-3621; toll-
free telephone 1-800-282-3713; direct telephone 503-230-3294; or e-mail
[pwsmith@bpa.gov]. Additional information can be found at BPA's Web
site: www.efw.bpa.gov.
SUPPLEMENTARY INFORMATION: The EIS will assess the environmental
consequences of the proposed project, including:
Interconnection agreement that BPA proposes with PE;
Construction and operation of the powerplant;
Construction and operation of an approximately 800-foot,
6-inch diameter gas line to tie into Williams Northwest Pipeline
Company's Plymouth Compressor Station pipeline;
Construction and operation of a rail spur near the
powerplant site for use during powerplant construction; and
Construction and operation of an interconnection
consisting of a substation and approximately one mile of 230-kV or 500-
kV transmission line from the substation to either the existing BPA
McNary-Big Eddy 230-kV transmission line or the proposed, new BPA
McNary-John Day 500-kV transmission line.
The powerplant and the gas and power interconnections would all be
located within Benton County, Washington.
Responsibility for construction and operation of the new facilities
is principally with PE who would build and operate the powerplant.
However, the transmission would be constructed under BPA's management,
and BPA would be responsible for the operation and maintenance of these
transmission facilities. Williams Northwest Pipeline Company would
build and operate the proposed approximately 800-foot gas pipeline that
would supply fuel to the powerplant.
Proposed Action: The Plymouth Generating Facility would be a
natural gas-fired, combined-cycle combustion turbine powerplant with a
nominal generating capacity of approximately 306 MW. The plant site
would be on approximately 44 acres zoned for agricultural use (with
energy projects permitted as conditional uses) and located about 6
miles west of Plymouth, Washington.
Natural gas would be burned in a gas turbine engine, in which the
expanding gases from combustion would turn the turbine's rotor, driving
a generator to produce electrical energy. Hot exhaust from the gas
turbine would be used to boil water using a heat recovery steam
generator (HRSG). Steam produced by the HRSG turns a steam turbine,
which would connect to another generator, producing additional
electrical energy.
The Plymouth Generating Facility would consist of a single gas
turbine generator, heat recovery steam generator and steam turbine
generator. Steam cycle cooling would utilize an air cooled condenser
and a conventional mechanical draft tower in combination to minimize
water use.
Water would be required to generate steam, for cooling and for
sanitary uses. The proposed powerplant would require 1,241 gallons per
minute of water under average conditions and use no more than 1000 acre
feet per year. PE proposes to use on-site wells and to return
wastewater flows from plant operations for agricultural irrigation.
PE proposes that project storm water be collected in retention and
filtration ponds located at the south side of the property.
The proposed Plymouth Generation Facility would deliver electricity
to the regional power grid through an interconnection with either the
existing
[[Page 2869]]
BPA McNary-Big Eddy 230-kV transmission line or the new, proposed BPA
McNary-John Day 500-kV transmission line.
Process to Date: BPA is the lead Federal agency for the joint NEPA/
SEPA EIS, and Benton County is the lead Washington State agency. Benton
County has received a SEPA Checklist and determined that preparation of
an EIS is required. Benton County has scheduled a public meeting to be
held on January 24, 2002, at Patterson, Washington, to obtain public
input concerning the scope of the EIS. An additional EIS scoping
meeting will be scheduled and announced by direct mail and through
local media.
Alternatives Proposed for Consideration: Alternatives thus far
identified for evaluation in the EIS are (1) the proposed action, (2)
alternative sites within the property under lease by PE, (3)
alternative transmission line interconnections, and (4) no action.
Other alternatives may be identified through the scoping process.
Identification of Environmental Issues: Benton County will prepare
an EIS consistent with its responsibilities under Chapter 43.21C of the
Revised Code of Washington and Chapter 197-11 of the Washington
Administrative Code. PE has requested transmission interconnection and
firm transmission service. Such an action triggers a need for BPA to
prepare NEPA documentation. Therefore, BPA and Benton County intend to
prepare a joint NEPA/SEPA EIS addressing both the powerplant and the
associated electric power interconnection and transmission facilities.
The principal issues identified thus far for consideration in the Draft
EIS are (1) air quality impacts, (2) aesthetic and visual impacts, (3)
socio-economic impacts including transportation impacts, (4) wetlands
and wildlife habitat impacts, (5) cultural resource impacts, (6) water
supply and quality impacts, (7) health and safety impacts, and (8)
noise impacts from plant operation. These issues, together with any
additional significant issues identified through the scoping process,
will be addressed in the EIS. BPA will also use the EIS and NEPA
process to address historic preservation and cultural resource issues
under Section 106 of the National Historic Preservation Act.
Public Participation: A public scoping meeting will be held at
Patterson, Washington, on January 24, 2002. Representatives of BPA and
Benton County will be available to receive oral and written public
comment. An additional meeting will be scheduled and announced by
direct mail and through local media. We request public and agency
comments on the scope of the EIS by March 15, 2002.
Receiving comments from interested parties will assure that BPA and
Benton County address in the EIS the full range of issues and
potentially significant impacts related to the proposed project. When
completed, a draft EIS will be circulated for review and comment, and
BPA and Benton County will hold at least one public comment meeting on
the draft EIS. BPA and Benton County will consider and respond in a
final EIS to comments received on the draft EIS.
Issued in Portland, Oregon, on January 11, 2002.
Stephen J. Wright,
Acting Administrator and, Chief Executive Officer.
[FR Doc. 02-1469 Filed 1-18-02; 8:45 am]
BILLING CODE 6450-01-P