Subject: Texas Eastern Transmission, LP; Notice of Intent To
[Federal Register: December 7, 2001 (Volume 66, Number 236)]
[Notices]
[Page 63531-63532]
>From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr07de01-28]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP02-17-000]
Texas Eastern Transmission, LP; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Freehold Project and Request
for Comments on Environmental Issues
December 3, 2001.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Freehold Project involving the
construction and operation of facilities by Texas Eastern Transmission,
LP (Texas Eastern) in Somerset and Hunterdon Counties, New Jersey.\1\
These facilities would consist of one 5,000 horsepower (hp) compressor
station and facilities related to the uprate of certain segments of its
mainline facilities east of Lambertville, New Jersey. This EA will be
used by the Commission in its decisionmaking process to determine
whether the project is in the public convenience and necessity.
---------------------------------------------------------------------------
\1\ Texas Easterns's application was filed with the Commission
on October 26, 2001, under Section 7 of the Natural Gas Act and Part
157 of the Commission's regulations.
---------------------------------------------------------------------------
If you are a landowner receiving this notice, you may be contacted
by a pipeline company representative about the acquisition of an
easement to construct, operate, and maintain the proposed facilities.
The pipeline company would seek to negotiate a mutually acceptable
agreement. However, if the project is approved by the Commission, that
approval conveys with it the right of eminent domain. Therefore, if
easement negotiations fail to produce an agreement, the pipeline
company could initiate condemnation proceedings in accordance with
state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' was attached to the
project notice Texas Eastern provided to landowners. This fact sheet
addresses a number of typically asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
It is available for viewing on the FERC Internet Web site
(www.ferc.fed.us).
Summary of the Proposed Project
Texas Eastern proposes to provide service to New Jersey Natural Gas
Company's local distribution system at Texas Eastern's Freehold Lateral
M&R Stations 953 and 2210. Texas Eastern proposes to:
Construct and operate a 5,000-horsepower electric motor-
driven compressor station in Somerset County, New Jersey (Freehold
Compressor Station);
Uprate the maximum allowable operating pressure of the 36-
inch-diameter Line No. 20 and the 42-inch-diameter Line No. 38 from 975
pounds per square inch gauge (psig) to 1,170 psig from milepost (MP)
0.0 to MP 13.9;
Install two pressure limiting devices at MP 13.9 of Line
Nos. 20 and 38, respectively; and
Replace five road crossings on Line No. 38 with heavier
wall thickness pipeline at the following locations in Somerset and
Hunterdon Counties, New Jersey:
County Road 605/Queens Road (MP 0.06);
State Route 31 (MP 2.69);
County Road 607/Rileyville Road (MP 6.12);
Montgomery Road (MP 9.37); and
Long Hill Road (MP 10.44).
The general location of Texas Eastern's proposed facilities is
shown on the map attached as appendix 1.\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies are available on the
Commission's website at the ``RIMS'' link or from the Commission's
Public Reference and Files Maintenance Branch, 888 First Street,
NE., Room 2A, Washington, DC 20426, or call (202) 208-1371. For
instructions on connecting to RIMS refer to the last page of this
notice. Copies of the appendices were sent to all those receiving
this notice in the mail.
---------------------------------------------------------------------------
Land Requirements for Construction
The proposed Freehold Compressor Station would be constructed on a
5-acre site which Texas Eastern would own. Texas Eastern indicated it
would need an additional 25 acres which it would acquire through
easements, for use as a noise buffer. Construction of the proposed
pressure limiting devices and the five road crossings would require a
total of about 6.9 acres of land, of which about 5.9 acres consist of
existing and maintained right-of-way. The remaining 1.0 acres of land
would be restored and allowed to revert to its former use.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
to discover and address concerns the public may have about proposals.
We \3\ call this ``scoping''. The main goal of the scoping process is
to focus the analysis in the EA on the important environmental issues.
By this Notice of Intent, the Commission requests public comments on
the scope of the issues it will address in the EA. All comments
received are considered during the preparation of the EA. State and
local government representatives are encouraged to notify their
constituents of this proposed action and encourage them to comment on
their areas of concern.
---------------------------------------------------------------------------
\3\ ''We,'' ``us,'' and ``our'' refer to the environmental staff
of the Office of Energy Projects.
---------------------------------------------------------------------------
The EA will discuss impacts that could occur as a result of the
construction and operation of the proposed project under these general
headings:
Geology and soils
Water resources, fisheries, and wetlands
[[Page 63532]]
Vegetation and wildlife
Endangered and and threatened species
Land use
Cultural resources
Air quality and noise
Public safety
We will also evaluate possible alternatives to the proposed project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to Federal, state, and local agencies, public
interest groups, interested individuals, affected landowners,
newspapers, libraries, and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission.
To ensure your comments are considered, please carefully follow the
instructions in the public participation section beginning on page 5.
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the proposed facilities and
the environmental information provided by Texas Eastern. This
preliminary list of issues may be changed based on your comments and
our analysis.
Potential impact on 3 Federally-listed threatened reptile
(1) and plant (2) species.
Conversion to industrial use of about 30 acres of land
that is registered with the New Jersey Green Acres program.
Proximity of the proposed facilities to homes and
residential land-use impacts.
Impact and routing of a 25 kilovolt electric service line,
about 1.5 miles long, to be installed by Public Service Electric & Gas
Company.
The Franklin Township Board of Education is in the process
of acquiring land for construction of a new high school within 0.25
mile of the proposed Freehold Compressor Station site.
Noise impacts due to operation of the proposed Freehold
Compressor Station.
Impact of operation of the proposed Freehold Compressor
Station on Franklin Township Board of Education's plan to construct a
new high school.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. By becoming a commentor, your
concerns will be addressed in the EA and considered by the Commission.
You should focus on the potential environmental effects of the
proposal, alternatives to the proposal (including alternative
locations), and measures to avoid or lessen environmental impact. The
more specific your comments, the more useful they will be. Please
carefully follow these instructions to ensure that your comments are
received in time and properly recorded:
Send an original and two copies of your letter to:
Secretary, Federal Energy Regulatory Commission, 888 First St., NE.,
Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas/
Hydro, PJ-11.3.
Reference Docket No. CP02-17-000; and
Mail your comments so that they will be received in
Washington, DC on or before January 15, 2002.
Comments, protests, and interventions may be filed electronically
via the Internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's web site under the ``e-Filing''
link.
If you do not want to send comments at this time but still want to
remain on our mailing list, please return the Information Request
(appendix 3). If you do not return the Information Request, you will be
removed from the environmental mailing list.
Due to current events, we cannot guarantee that we will receive
mail on a timely basis from the U.S. Postal Service, and we do not know
how long this situation will continue. However, we continue to receive
filings from private mail delivery services, including messenger
services in a reliable manner. The Commission encourages electronic
filing of any comments or interventions or protests to this proceeding.
We will include all comments that we receive within a reasonable time
frame in our environmental analysis of this project.
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an official party to the proceeding known as an
``intervenor.'' Intervenors play a more formal role in the process.
Among other things, intervenors have the right to receive copies of
case-related Commission documents and filings by other intervenors.
Likewise, each intervenor must provide 14 copies of its filings to the
Secretary of the Commission and must send a copy of its filings to all
other parties on the Commission's service list for this proceeding. If
you want to become an intervenor you must file a motion to intervene
according to Rule 214 of the Commission's Rules of Practice and
Procedure (18 CFR 385.214) (see appendix 2). Only intervenors have the
right to seek rehearing of the Commission's decision.
Affected landowners and parties with environmental concerns may be
granted intervenor status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which would not be
adequately represented by any other parties. You do not need intervenor
status to have your environmental comments considered.
Copies of this filing are on file with the Commission and are
available for public inspection. This filing may also be viewed on the
Web at http://www.ferc.gov using the ``RIMS'' link, select ``Docket #''
and follow the instructions (call 202-208-2222 for assistance).
Similarly, the ``CIPS'' link on the FERC Internet website provides
access to the texts of formal documents issued by the Commission, such
as orders, notices, and rulemakings. From the FERC Internet website,
click on the ``CIPS'' link, select ``Docket#'' from the CIPS menu, and
follow the instructions. For assistance with access to CIPS, the CIPS
helpline can be reached at (202) 208-2474.
Linwood A. Watson, Jr.,
Acting Secretary.