Subject: Starbuck Power Project
[Federal Register: June 14, 2001 (Volume 66, Number 115)]
[Notices]
[Page 32339-32340]
>From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr14jn01-58]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Bonneville Power Administration
Starbuck Power Project
AGENCY: Bonneville Power Administration (BPA), Department of Energy
(DOE).
ACTION: Notice of intent to prepare an Environmental Impact Statement.
-----------------------------------------------------------------------
SUMMARY: This notice announces BPA's intention to prepare a joint
National Environmental Policy Act (NEPA)/State Environmental Policy Act
(SEPA) EIS in cooperation with the State of Washington Energy Facility
Site Evaluation Council (EFSEC) for an electrical interconnection
including a new 16-mile 500-kilovolt (kV) transmission line and other
facilities associated with a proposed power plant. BPA is the lead
Federal agency under NEPA and EFSEC is the lead Washington State agency
under SEPA. The Starbuck Power Project is a 1,200-megawatt (MW)
generating station proposed by Starbuck Power Company, L.L.C. (SPC)
that would be located near the town of Starbuck in Columbia County,
Washington. SPC has requested an interconnection and upgrade to BPA's
transmission system that would allow firm power delivery to the
wholesale power market. BPA proposes to execute an agreement with SPC
to provide the interconnection and firm power transmission.
ADDRESSES: To be placed on the project mailing list, including
notification of proposed meetings, call toll-free 1-800-622-4520, name
this project, and leave your complete name and address. To comment,
call toll-free 1-800-622-4519; send an e-mail to the BPA Internet
address comment@bpa.gov; or send a letter to Communications, Bonneville
Power Administration--KC-7, P.O. Box 12999, Portland, Oregon, 97212.
FOR FURTHER INFORMATION CONTACT: Lou Driessen, Project Manager,
Bonneville Power Administration--TNP-3, P.O. Box 3621, Portland,
Oregon, 97208-3621; toll-free telephone 1-800-282-3713; direct
telephone 503-230-5525; or e-mail lcdriessen@bpa.gov. You may also
contact Phil Smith, Environmental Coordinator, Bonneville Power
Administration--KEC-4, P.O. Box 3621, Portland, Oregon 97208-3621;
toll-free telephone 1-800-282-3713; direct telephone 503-230-3294; or
e-mail pwsmith@bpa.gov. Additional information can be found at BPA's
web site: www.efw.bpa.gov.
SUPPLEMENTARY INFORMATION: The EIS will assess the environmental
consequences of the proposed project, including:
Interconnection agreement that BPA proposes with SPC;
Construction and operation of the power plant;
Construction and operation of an approximately 200-foot,
20-inch-diameter gas line to tie into Pacific Gas & Electric (PG&E) Gas
Transmission Northwest's (GTN) pipeline;
Construction and operation of an on-site well, or in the
alternative, an approximately 6-mile long, 4-inch diameter water supply
line from the town of Starbuck to the power plant site;
Construction and operation of a rail spur near the power
plant site for use during power plant construction; and
Construction and operation of an interconnection
consisting of a substation and approximately 16 miles of 500-kV
transmission line from the substation to Lower Monumental Substation.
The power plant and the gas and power interconnections would be
located within Columbia County, Washington. Approximately 1 mile of the
new 500-kV transmission line would be located in Columbia County with
the remaining 15 miles in Walla Walla County, Washington.
Responsibility for construction and operation of the new facilities
is principally with SPC who would build and operate the power plant.
However, the interconnection and the new 500-kV transmission line would
be constructed under BPA's management, and BPA would be responsible for
the operation and maintenance of these facilities. GTN would build and
operate the proposed approximately 200-foot gas pipeline that would
supply fuel to the power plant.
Proposed Action
The Starbuck Power Project would be a natural-gas-fired combined-
cycle combustion turbine power plant with a nominal generating capacity
of approximately 1,200 MW. The plant site would be located on
approximately 50 acres of a 100-acre site that is zoned for industrial
use and which is located approximately 6 miles northwest of Starbuck,
Washington, on property under option and owned by the BAR-Z Ranch, a
Washington Corporation.
Natural gas would be burned in a gas turbine engine, in which the
expanding gases from combustion would turn the turbine's rotor, driving
a generator to produce electrical energy. Hot exhaust from the gas
turbine would be used to boil water, using a heat recovery steam
generator (HRSG). Steam produced by the HRSG turns a steam turbine,
which would connect to another generator, producing additional
electrical energy.
The Starbuck Power Project would consist of two complete and
separate combined cycle power blocks (or ``islands'') and associated
support facilities. In summary, each block would consist of two gas
combustion turbine generators, two HRSGs, one steam turbine generator,
and one air-cooled condenser.
Water would be required to generate steam, as well as for sanitary
uses. The proposed power plant would require an average water
consumption rate of less than 500,000 gallons per day (gpd). SPC
proposes to use an on-site well. As an alternative, the project has
secured an option to purchase 100 gallons per minute (gpm), or up to
144,000 gpd, of water from the town of Starbuck's existing water right.
With this alternative, an approximately 5-mile water pipeline would be
constructed from the town of Starbuck to the project site. SPC proposes
to locate this line within an abandoned railroad right-of-way that
parallels SR-261 from Starbuck to just south of the project site.
SPC proposes that project wastewater and storm water be collected
in retention and infiltration ponds located at the south end of the
property.
The proposed Starbuck Power Project would deliver electricity to
the regional power grid through an interconnection and a new 500-kV
transmission line paralleling the existing Lower Monumental-Little
Goose No. 1 and No. 2 transmission lines. BPA would also modify the
existing Lower Monumental Substation.
[[Page 32340]]
Process to Date
BPA is the lead Federal agency for the joint NEPA/SEPA EIS, and
EFSEC is the lead Washington State agency. EFSEC has already held open
houses introducing the Starbuck Power Project to interested parties in
Columbia County and the surrounding area. Subsequent to these meetings,
BPA determined that a new 500-kV transmission line was necessary for
firm power delivery on the existing transmission system. SPC will
prepare an Application for Site Certification and submit it to EFSEC in
July 2001. This initial application will address the Starbuck Power
Project in detail. BPA and EFSEC will conduct joint scoping meetings
after receipt and preliminary review of the initial submission.
Alternatives Proposed for Consideration
Alternatives thus far identified for evaluation in the EIS are (1)
the proposed actions, (2) use of the town's well and a proposed water
pipeline as an alternative to the on-site well, and (3) no action.
Other alternatives may be identified through the scoping process.
Identification of Environmental Issues
EFSEC will prepare an EIS consistent with its responsibilities
under Chapter 80.50 of the Revised Code of Washington and Chapter 197-
11 of the Washington Administrative Code. BPA has determined in a
System Impact Study requested by SPC that, for firm transmission
service, the construction of 16 miles of 500-kV transmission line may
be required. Such an action triggers a need for BPA to prepare an EIS.
Therefore, BPA and EFSEC intend to prepare a joint NEPA/SEPA EIS
addressing both the power plant and the associated electric power
interconnection and transmission facilities. The principal issues
identified thus far for consideration in the Draft EIS are (1) air
quality impacts, (2) aesthetic and visual impacts, (3) socio-economic
impacts including transportation impacts, (4) wetlands and wildlife
habitat impacts, (5) cultural resource impacts, (6) water supply and
quality impacts, (7) health and safety impacts, and (8) noise impacts
from plant operation. These issues, together with any additional
significant issues identified through the scoping process, will be
addressed in the EIS. BPA will also use the EIS and NEPA process to
address historic preservation and cultural resource issues under
Section 106 of the National Historic Preservation Act.
Public Participation
After July 2001, one or more EIS scoping meetings will be held, and
a 45-day comment period will be announced, during which affected
landowners, concerned citizens, special interest groups, local
governments, and any other interested parties are invited to comment on
the scope of the proposed EIS. A 30-day notice of the meeting(s),
including time and location, will be provided to interested persons. At
the meeting(s), BPA and EFSEC will answer questions and accept oral and
written comments.
Receiving comments from interested parties will assure that BPA and
EFSEC address in the EIS the full range of issues and potentially
significant impacts related to the proposed project. When completed,
the Draft EIS will be circulated for review and comment, and BPA and
EFSEC will hold at least one public comment meeting on the Draft EIS.
BPA and EFSEC will consider and respond in the Final EIS to comments
received on the Draft EIS.
Issued in Portland, Oregon, on June 4, 2001.
Stephen J. Wright,
Acting Administrator and Chief Executive Officer.
[FR Doc. 01-14989 Filed 6-13-01; 8:45 am]
BILLING CODE 6450-01-P