We Almost Lost Shasta Watershed
Rancho Seco Near-Disaster Covered Up by Utility
On December 26th, 1985 at 4:17 A.M., the Rancho Seco reactor located
southeast of Sacramento came extremely close to a meltdown. The reactor with a
hundred accidents under its belt (twice the average for reactors its age) and
three of the most serious cooldowns in the industry has created a political and
economic crisis for the Sacramento Municipal Utility Commission (SMUD) that
may lead to the permanent shutdown of the reactor or even bankruptcy of the
utility. It has been shutdown since the accident, and only has a 40% chance of
coming back on line by June 1987. The accident did not come to the public's
attention until after the Chernobyl disaster. What's most chilling however,
is the fact that the public never learned just how serious the accident was.
In piecing together the events from the NRC's own investigation, it becomes
clear that the event was far more serious than a mere mechanical foul-up, as
claimed by SMUD. The accident, caused by a loose wire, cut off power to the
Integrated Control System (ICS) for 26 minutes. The ICS is the computer system
that regulates the temperature of the reactor and the steam system to the
turbine generator. In other words, the operators lost control of the reactor
from the control room.
Workers were dispatched to various parts of the facility in attempts to
head off a loss of coolant accident (LOCA). LOCA's are the dreaded scenario
almost sure to lead to a meltdown. Two of the workers were contaminated in
their attempt to reach critical valves.
Operators were successfull at stopping the LOCA but did not have accurate
preocedures for maintaining control of the reactor from outside the control
room. As a result, the reactor vessel cooled down to quickly. When this occurs,
the 8 inch thick walls of the reactor may shatter, crack or become embrittled
reducing the usable lifetime for the unit. During the accident the following
serious events ocurred:
- At 4:52 AM, at the height of the crisis, a back-up shift operator
collapsed and had tobe taken to the hospital. The shift was at a bare minimum
level before his collapse.
- Attempts to call for help were useless because the switch-board operator
on duty did not have the phone numbers of the next shift.
- No alarm was sounded within the facility, so the Rad/Chem team did not do
monitoring for contamination during the most crucial stages of the accident.
Contanubated areas were not cordoned off, resulting in the dosing of an unaware
security guard.
- Required updates of the accident to state emergency officials weren't
done, nor were they given correct details of the accident to allow proper
emergency response preparations.
- The alarm system in the control room was so loud that operators could not
hear themselves talk, increasing the tension during the crisis. The alarms
were shut off but not properly reset to warn of further problems.
- There was radioactive contamination of the Auxiliary Building and releases
of radiation offsite. The utility estimated that 33 curies of noble gases were
released to the environment. The 30 curies of Xenon that were released,
rapidly turn into radioactive Iodine. The NRC and SMUD claimed this amount
would not do damage to the environment.
- The stack radiation monitors at the complex that were set at 60,000 counts
per minute (CPM) were tripped at 5:05 AM, setting off state emergency alarms in
Sacramento (the 60,000 CPM level is 7,500 times higher than normal background
radiation). The monitor levels were supposed to be set at 20,000 CPM rather
than at 60,000 CPM. Another of the monitors had run out of ink, making it
impossible to get accurate release readings. The true level of offsite
radiation releases is clearly in question.
- Damage included destruction of a large make-up pump that burned at the
start of the incident. Core Assemblies in the reactor were also lifted from
their normal positions. The investigations showed that there was no seriouis
damage to the reactor core.
- During the remote manipulation of the valves, one valve was stuck in the
open position and unable to be closed. Another valve was turned off by one
operator, but broken back into the open position when another operator by,
thinking the valve still open. Operators were later given training in proper
operation of valves. Another pump that was part of the reason for the rapid
cooldown was completely forgotten to be turned off.
- No log was kept during the accident because the operators were too busy
trying to deal with the accident. Operator coments registered with the NRC
called SMUD training "terrible" and complained of complacent
management. Quizzing of operators showed extensive weaknesses in a variety of
procedures for running the reactor.
The details of the accident left the NRC strongly concerned about whether
or not such a small utility as SMUD couldsafely opoerate a reactor. Their
statement that the reactor was equivalent to a car being driven for 150,000
miles without a tune-up is a strong analogy for a very dangerous threat to
Californians. The NRV went on to fine SMUD over $600,000 in penalties due to
violations of NRC procedures and regulations. An outcome of the evaluation of
the accident included the discovery that SMUD ignored sumptoms from the ICS in
a similar incident on Decmeber 5, 1985. The NRC listed 38 issues, of which 18
had been closed by May 1986, that had to be cleared before the reactor would be
allowed to be restarted.
The accident was not an isolated occurrance. Rancho Seco has had a
steadily increasing number of mishaps and violations that started when the
reactor was first opened in 1975. Some of the highlights of Rancho Seco:
- Three of the worst overcooling incidents in U.S. history, with the
1st, 3rd and 9th worst accidents on record.
- Two workers were killed from a June 1984 steam pipe rupture similar to the
one that killed 4 people at the Surry reactor in Virginia in 1986.
- 13 million gallons of radioactive effluent were dumped into the nearby
Clay Creek due primarily to waste storage capacity problems.
- A class action suit was filed against the utility by 142 residents living
near the reactor for damages to health, property and livestock (the suit is
still underway).
- Changes mandated by the NRC in the wake of the Three Mile Island Accident
have not all been completed.
- Outright lying to the NRC may have ocurred. In the latest case the NRC is
investigating possible falsification of improperly laid back-up safety wiring.
The utility may be forced to rewire much of the 250,000 miles of wire at the
reactor if the back-up safety system wiring was not routed differently from the
primary safety wiring.
- Rancho Seco has one of the worst operating levels in the U.S. It has
operated only 42% of the time during its first 11 years. It has not operated
at all during its twelfth year. The NRC has classified the reactor as one of
the worst 5 in the country.
- Maintenance personnel were poorly trained and as a result, poor
maintenance practices throughout the facility have been ocurring for years. One
worker was found unable to correctly read gauges. One of the valves involved
in the December accident was also found to have not been given any preventive
maintenance care for 11 years.
- In 1980, the Polar Crane cable snapped as it was holding a 3,000 Pound
metal plate, just barely missing the reactor. The plate was lifted 10 feet off
the gound when regulations only allowed for 6 inches. The crane had been
lifting a 7 ton weight over the spent fuel pond prior to the above incident.
- Problems at Rancho Seco date from the initial decision to build a Babcock
and Wilcox reactor, a twin to the reactor at Three Mile Island, which suffered
the worst accident to date in the U.S. B&W reactors are known to be the
most delicately built reactors in the country and are susceptable to severe
problems if not properly maintained.
After the Chernobyl accident, an in depth look at the reactor by the local
media created a strong concern in the Sacramento area for the shutdown of the
reactor. In an October 1986 poll, 55% of the residents did not want the
reactor to be reopened. Sacramentans for Safe Energy has mounted an initiative
drive that would permanently shut down Rancho Seco. They are well on their way
to collecting the 40,000 signatures needed to hold a special election before
SMUD will be able to get the reactor ack on line. The utility has used the
claim that it would cost ratepayers an additional 84% increase in rates besides
the cost of decommissioning, if Rancho Seco never reopens. Ratepayers will
have already been hit up with a 50% rate increase during the down time of the
reactor.
Failure of the initiative will lead to the likely reopening of the reactor
by the NRC (who has pulled only two other reactor liecenses in its recent
history-- The Vallacitos reactor Hayward and the Humboldt reactor near Arcata,
Ca.){since then Peachbottom I had its license removed in late 87}. If the
reactor does reopen it will jeopardize the lives of more than eight million
people around central California. Aprimary water source for the entire East
Bay is less than 15 milles downwind of the reactor. This area is also one of
the largest agricultural regions in the United States. Dr. John Gofman, the
noted health-physicist has suggested that Northern Californians migrate if
Rancho Seco is allowed to be put back on line. The Abalone Alliance Clearhouse
agrees.
Sources: Sacramento Bee, San Jose Mercury News & Nuclear Regulatory
Commission accident report
Produced by the Abalone Alliance Clearinghouse office Spring 1986